Case studyIndia

Food Plant Feasibility Study in India: A Techno-Economic Worked Example for a Snack Plant

A food plant feasibility study tells a brand whether a plant is worth building before money is committed. This worked example follows a hypothetical snack brand from brief to decision: demand and price, sourcing, licence band, capex and opex, then IRR, NPV, payback and sensitivity cases[1]. Every input is assumed and every result is calculated; no client data is shown.
SIDr Shreya Iyer
PhD (Food Science) · Director of New Product Development, Food Research Lab
✓ Technically reviewed by FRL Editorial · Last reviewed: 16 November 2026 · Next review: May 2027
Posted
16 November 2026

Last checked
16 November 2026

Reading time
10 min

Sources
7
At a glance
  • Labelled worked example: Brand X (hypothetical) tests a 3-tonne-a-day pulse-and-soy snack plant against staying with its co-packer; all inputs assumed.
  • Total project cost ₹800 lakh (₹700 lakh capex plus ₹100 lakh working capital); EBITDA ₹204 lakh at 80% utilisation (calculated).
  • Base case: IRR 14.0%, NPV ₹75.9 lakh at 12%, payback about 5.5 years (calculated).
  • A 5% price fall turns NPV to −₹181.6 lakh; a 10% capex overrun leaves it just positive.
  • Licence band follows FSSAI’s 2026 turnover thresholds, not national sales[1].
Key numbers
Total project cost (assumed)
₹800 lakh (capex ₹700 lakh + working capital ₹100 lakh)
Base-case IRR, 10 years (calculated)
14.0%
Base-case NPV at 12% (calculated)
₹75.9 lakh
Payback (calculated)
≈ 5.5 years
Measured results on this page
None (worked example)

About this worked example

This is a labelled worked example, not a client case study. Brand X is a hypothetical brand, and every input on this page (plant size, price, costs, tax rate, discount rate) is an assumption. The returns are calculations from those assumptions, not measured or reported results. The page shows how Food Research Lab structures a food plant feasibility study in India: demand and price, technical design, approvals, capex and opex, returns and sensitivity testing.

For the service behind it, see our techno-economic feasibility study page. For other labelled worked examples, see the retort soup pilot trial and kitchen-to-pilot-plant scale-up.

The brief: build a plant or keep the co-packer?

Brand X, a packaged-snack brand that today buys from co-packers, asks one question: should it build its own plant for a pulse-and-soy ready-to-eat snack? The study has to give a yes, a no or a “not yet”, and show which assumptions decide the answer.

Table 1. Worked-example brief (all values assumed)

Item Assumption
Product Pulse-and-soy ready-to-eat snack, ambient, six-month shelf life target
Capacity 3 tonnes a day, 300 operating days (900 tonnes a year at full capacity)
Location A pulse-growing region, with raw material bought within a contracted radius
Selling price ₹180 per kg ex-factory
Capacity utilisation 50% in year 1, 70% in year 2, 80% from year 3
Model horizon and hurdle rate 10 years; 12% discount rate; 25% tax rate
Incentives None included in the cash flows

No production-linked incentive is modelled. Ready to Cook/Ready to Eat foods are one of the four product segments of the Production Linked Incentive Scheme for Food Processing Industry (PLISFPI), approved in March 2021 with an outlay of ₹10,900 crore for 2021-22 to 2026-27[2][3]. The Ministry of Food Processing Industries ran beneficiary selection as a one-time exercise[3], so a new plant should not count on it. Scheme context is covered in our cluster guide to the food processing industry in India in 2026.

Step 1: demand, price and capacity utilisation

The study turns the market view into three inputs: price, volume and how fast the plant fills. Brand X already sells the product through co-packers, so the assumed ₹180 per kg ex-factory price and the ramp to 80% utilisation by year 3 rest on its own sales history; a new entrant would need primary market research before setting them. At 80% utilisation the plant makes 720 tonnes a year, or ₹1,296 lakh of revenue (720,000 kg × ₹180).

Positioning is checked at the same stage. A 2024 mapping study found that Indian research often uses “ready-to-eat” as a descriptor for ultra-processed foods, and that packaged traditional recipes also carried ultra-processed ingredients[4]. The ingredient list is therefore a positioning decision as well as a cost line, and it is fixed before the price is.

Step 2: technical design, sourcing and approvals

Raw material sets the location. Soybean output in India varies widely from year to year and district to district, with recent swings linked to extreme rain and drought in major producing districts[5]. Pulse production trends also differ by state: one forecasting study projected growth in Rajasthan and Madhya Pradesh but declines in Karnataka, Maharashtra and Uttar Pradesh to 2030[6]. The plant is therefore sited for a contracted sourcing radius, with a second supply region named in the model.

Machinery, utilities and layout

Machinery is sized for 3 tonnes a day. Utilities cover power, water and steam, and the layout separates raw-material, process and packed-product zones so that hygiene and allergen controls (soy is a declared allergen) are designed in rather than added later. Supplier quotes replace the assumed capex before any decision.

Licence category and approvals

The writer’s draft assumed that national sales meant a central FSSAI licence. That is not the test. Under the Food Safety and Standards (Licensing and Registration of Food Businesses) Amendment Regulations, 2026 (Gazette notification of 10 March 2026) and FSSAI’s order of 13 March 2026, the turnover bands from 1 April 2026 are: registration up to ₹1.5 crore, state licence above ₹1.5 crore and up to ₹50 crore, and central licence above ₹50 crore[1]. Licences and registrations issued from that date have perpetual validity[1]. At about ₹13 crore a year, the plant alone would sit in the state band, but the category is confirmed on FoSCoS against the business’s declared turnover and kind of business before filing[1][7]. Factory plan approval and pollution consents to establish and to operate run on the same timeline; our guide to the FSSAI licence and other approvals for a food processing plant sets out the sequence, and FRL’s state licence support covers the filing.

Pre-launch testing (identity, safety, nutrition and shelf life) is a budget line, not an afterthought. Our pillar guide to food testing before launch lists what to test, and our guide to real-time and accelerated shelf-life testing covers the six-month claim.

Step 3: capex and opex estimates

The capex and opex model uses assumed figures that supplier quotes would replace (Tables 2 and 3). Total project cost is ₹800 lakh: ₹700 lakh of capex plus ₹100 lakh of working capital.

Table 2. Capex (₹ lakh, assumed)

Item ₹ lakh
Land (100) and building (150) 250
Plant and machinery 300
Utilities 60
Pre-operative expenses 40
Contingency 50
Capex 700
Working capital (recovered in year 10) 100
Total project cost 800

Table 3. Operating year at 80% utilisation (₹ lakh, calculated from assumptions)

Line ₹ lakh Basis
Revenue 1,296.0 720 t × ₹180/kg
Raw material and packaging 712.8 55% of revenue (₹99/kg)
Other variable costs (utilities, consumables, freight) 259.2 20% of revenue (₹36/kg)
Fixed costs (salaries, maintenance, overheads) 120.0 Assumed
EBITDA 204.0 15.7% margin
Depreciation 60.0 ₹600 lakh depreciable (capex less land), straight line over 10 years
Tax 36.0 25% of (EBITDA − depreciation)
Operating cash flow 168.0 EBITDA − tax

The EBITDA breakeven sits near 30% utilisation (₹120 lakh of fixed costs ÷ a 25% contribution margin on ₹1,620 lakh of revenue at full capacity ≈ 29.6%). Depreciation is simplified to a straight line; a bankable report would follow the Income-tax Act’s depreciation rules and the lender’s format.

Step 4: IRR, NPV and payback

With a 25% tax rate and a 12% discount rate, the base case gives an internal rate of return (IRR) of 14.0%, a net present value (NPV) of ₹75.9 lakh and a payback period of about 5.5 years (Table 4, Figure 1). IRR is the discount rate at which NPV is zero; payback is the point at which cumulative cash flow turns positive.

Table 4. Base-case cash flows (₹ lakh, calculated)

Year Utilisation Revenue EBITDA Tax Cash flow Cumulative
0 – – – – −800.0 −800.0
1 50% 810.0 82.5 5.6 76.9 −723.1
2 70% 1,134.0 163.5 25.9 137.6 −585.5
3 to 9 (each) 80% 1,296.0 204.0 36.0 168.0 −417.5 (yr 3) to +590.5 (yr 9)
10 80% 1,296.0 204.0 36.0 268.0 (incl. working capital) +858.5

Cumulative cash flow is −₹81.5 lakh at the end of year 5 and +₹86.5 lakh at the end of year 6, so payback is 5 + 81.5 ÷ 168 ≈ 5.5 years. No terminal value is included. The return clears the 12% hurdle by two percentage points: positive, but thin.

Line chart of Brand X cumulative cash flow in rupees lakh from minus 800 in year 0 to about plus 860 in year 10, crossing zero at a payback of about 5.5 years
Figure 1. Brand X cumulative cash flow, base case (calculated from assumed inputs; illustrative, not project results). Source: FRL.

Step 5: sensitivity testing

A base case alone does not support a decision. The study moves one assumption at a time (Table 5). In the price case, costs per kilogram stay the same while the selling price falls.

Table 5. Sensitivity of Brand X returns (calculated)

Case NPV at 12% (₹ lakh) IRR Payback (years)
Base case 75.9 14.0% 5.5
Selling price down 5% (₹171/kg) −181.6 6.9% 7.6
Raw material and packaging cost up 5% −63.6 10.3% 6.4
Utilisation 70% from year 3 −44.4 10.8% 6.3
Capex up 10% (₹770 lakh) 14.3 12.4% 5.8

NPV falls to zero at a selling price of about ₹177 per kg (1.5% below base) or at about 74% utilisation from year 3. A 10% capex overrun still leaves NPV just positive, while a 5% price fall wipes out ₹257 lakh of value. Price and raw-material cost move the answer far more than capex does.

What the food plant feasibility study concluded

On these assumptions, Brand X’s own plant clears the 12% hurdle only narrowly and fails under a 5% price fall, a 5% rise in raw-material and packaging cost, or utilisation stuck at 70%. The study’s answer is “not yet”: stay with co-packers until a price agreement with buyers and a pulse and soy supply contract are signed, then re-run the model with supplier quotes.

  • Start with the decision, not the spreadsheet: build or buy, and on what evidence.
  • Replace every assumption with a quote or a contract before the board meets.
  • Negotiate price and raw material first; they move NPV more than capex.
  • Check the licence band against the current FSSAI thresholds, not against where the product will be sold.
  • Show assumptions and sensitivities openly so a lender can test them; the same chapters (market, technical, cost, returns) form the core of a detailed project report (DPR).

For brands & formulators

Food Research Lab, based in Chennai, India, prepares techno-economic feasibility studies for proposed food processing plants. Our report covers raw material procurement and costing, machinery and processing costs, profit and loss analysis, product pricing, packaging and nutrition labelling, and is written so that promoters can submit it to their banks for loan approvals and capital subsidy applications. Our feasibility page states that our consultants have worked on more than 50 such studies.

Where the product is not yet fixed, our new food product development team sets the recipe and process first, our regulatory research team maps licences and approvals, and testing is run or arranged through accredited partner laboratories. If building is not yet justified, see our food contract manufacturing services. See also our India services.

Contact us with your product, target capacity and location.

What to do now
  • ✓Write the decision first: build, buy from a co-packer, or wait.
  • ✓Replace assumptions with quotes for machinery, utilities and raw material.
  • ✓Run price, raw-material, utilisation and capex sensitivities before the board meeting.
  • ✓Check your FSSAI licence band against the 2026 turnover thresholds on FoSCoS[1].
  • ✓Talk to our techno-economic feasibility team about your plant.
Your next step
Test your plant before you build it
1Send your product, target capacity, location and any supplier quotes.
2FRL models demand, sourcing, capex, opex and returns, with sensitivity cases and the approvals path.
3Receive a feasibility report you can take to your board and your bank.
Questions brands ask
Is this a real FRL client project?

No. It is a labelled worked example. Brand X is hypothetical, and the plant size, price, costs, tax rate and discount rate are assumptions. The IRR, NPV, payback and sensitivity results are calculations from those assumptions, not measured or reported outcomes. The page shows how FRL structures a food plant feasibility study in India.

What is a techno-economic feasibility study?

It is a structured assessment of whether a proposed plant is technically workable and financially viable. It combines market demand and price, process and capacity design, raw material sourcing, capex and opex, and returns such as IRR, NPV and payback, then tests how those returns change when key assumptions move.

What does a food plant feasibility study include?

Typically: demand, price and capacity utilisation; product and process design; machinery, utilities and layout; raw material sourcing; licences and approvals; capex, working capital and operating costs; and returns with sensitivity cases. FRL’s reports also cover product pricing, packaging and nutrition labelling, written so promoters can submit them to banks.

Does a food plant selling across India need an FSSAI central licence?

Not because of where it sells. From 1 April 2026, FSSAI’s turnover bands are registration up to ₹1.5 crore, state licence above ₹1.5 crore up to ₹50 crore, and central licence above ₹50 crore. Confirm the category on FoSCoS against your declared turnover and kind of business before filing.

How are IRR and payback calculated for a food plant?

Both come from projected annual cash flows after tax. IRR is the discount rate at which the net present value of all cash flows, including the initial investment, equals zero. Payback is the time until cumulative cash flow turns positive. In this example they are 14.0% and about 5.5 years.

Which assumptions matter most in a food plant feasibility study?

In this example, selling price and raw-material cost. A 5% price fall turned NPV from ₹75.9 lakh to −₹181.6 lakh, while a 10% capex overrun still left NPV just positive. That is why price and supply contracts are negotiated before the plant is committed.

References
  1. Food Safety and Standards Authority of India. (2026, March 27). FAQs on Food Safety and Standards (Licensing and Registration of Food Businesses) Amendment Regulations, 2026 (File No. RCD-01002/1/2021-Regulatory-FSSAI-Part(1)). https://www.fssai.gov.in/upload/advisories/2026/03/69c6a23234827order_27032026.pdf (cited for the Gazette notification of 10 March 2026, the order of 13 March 2026, the turnover bands effective 1 April 2026 and perpetual validity)
  2. Press Information Bureau, Ministry of Food Processing Industries. (2026, April 7). Production Linked Incentive Scheme for Food Processing Industry (PLISFPI): A major push for India’s food processing industry. https://www.pib.gov.in/PressReleasePage.aspx?PRID=2249621 (cited for the four Category I segments, including Ready to Cook/Ready to Eat foods)
  3. Press Information Bureau, Ministry of Food Processing Industries. (2024, December 6). Production linked incentive scheme for food processing industries. https://www.pib.gov.in/PressReleasePage.aspx?PRID=2081393 (cited for Cabinet approval on 31 March 2021, the ₹10,900 crore outlay for 2021-22 to 2026-27 and beneficiary selection as a one-time exercise)
  4. Ghosh-Jerath, S., Khandpur, N., Kumar, G., Kohli, S., Singh, M., Bhamra, I. K., Marrocos-Leite, F. H., & Reddy, K. S. (2024). Mapping ultra-processed foods (UPFs) in India: A formative research study. BMC Public Health, 24(1), 2212. https://doi.org/10.1186/s12889-024-19624-1 (cited for “ready-to-eat” used as a UPF descriptor and UPF ingredients in packaged traditional recipes)
  5. Prashnani, M., Dupare, B., Vadrevu, K. P., & Justice, C. (2024). Towards food security: Exploring the spatio-temporal dynamics of soybean in India. PLOS ONE, 19(5), e0292005. https://doi.org/10.1371/journal.pone.0292005 (cited for high variability in soybean production linked to extreme rain and drought)
  6. Mishra, P., Al Khatib, A. M. G., Lal, P., Anwar, A., Nganvongpanit, K., Abotaleb, M., Ray, S., & Punyapornwithaya, V. (2023). An overview of pulses production in India: Retrospect and prospects of the future food with an application of hybrid models. National Academy Science Letters, 1–8. https://doi.org/10.1007/s40009-023-01267-2 (cited for state-level pulse production forecasts to 2030)
  7. Food Safety and Standards Authority of India. (n.d.). FoSCoS: Food Safety Compliance System. Retrieved 16 November 2026, from https://foscos.fssai.gov.in/ (cited as the portal for licence and registration applications)
Continue the series · Part 5 of 5

Setting up a food plant in India

1
Food processing industry in India in 2026

PLISFPI, PMKSY and where capacity is being added.
2
FSSAI central licence for a food processing plant

The licence, factory and pollution approvals a new plant needs.
3
Food testing before launchMAIN GUIDE

What to test before a new product reaches the market.
4
How much does a food recall cost?

The direct and indirect costs a launch can carry.
5
Food plant feasibility study in IndiaYou are here